Large "For Sale" sign coming to Kindersley. |
Here are some quick notes:
- Some of the services along Clarke Dr is about 6.5 metres (20') deep,
- to do this work a long ditch is dug in which a high-low works about 3 metres down and then digs down a further 3 metres or so.
- One street's digging is complete;
- The water, sewer, and storm water pipelayers arrive this week and they need 46 working days to lay all of the pipe;
- After the pipe is laid then gravel will be hauled to develop the base for the road
- Once the base is complete then the gutter, curb, and sidewalk will be constructed.
- That is the infrastructure work for this year.
- While this work is being done houses can be built.