We received
the engineers report late in the week. What follows are some highlights. Some of the paragraphs are AE and some have been summarized by me.
Before looking at the highlights please consider policy GP.0. from Council's Policy Manual:
The purpose of Council, on behalf of the ratepayers of Kindersley, is to see to it that the Town of Kindersley (a) achieves appropriate results for appropriate persons at an appropriate cost and (b) avoids unacceptable actions and situations.
·
The
purpose of the visual inspection was to assess the condition of the existing
exterior filter room masonry block wall as well as the exterior stairway
attached to this wall, in order to determine the cause of the cracking and
identify elements that need to be repaired and/or replaced for the continued
use of the Aquatic Centre.
Crack in wall of filter room. |
Background
·
Based
on the drawings by Midland Industrial Structures Ltd received from Town
officials, the Kindersley Aquatic Centre was constructed in 1975. Drawings P-1,
A-1 to A-4, S-1, and S-2 were made available for review.
·
The
walls are made of lightweight ungrouted and unreinforced hollow blocks with
prefabricated steel columns. (met the code of the day)
·
The
upper portion of the north wall overlooking the pool was enclosing the mezzanine was added in 2004.
·
Based
on recommendations from C.A. Reed & Associates, in 2009 the Town decided to
remove the existing building structure from GL-4 to GL-8 after concerns were
raised regarding the structural integrity of the building due to steel
corrosion.
Visual Inspection
·
A visual inspection of the Kindersley
aquatic centre was conducted on the morning
of May 27, 2014 by Associated Engineering.
·
In addition to the filter room exterior
masonry block wall and the exterior staircase, the inspection included
the women's change
room and the southwest exterior
wall due to concerns over cracked masonry
blocks.
Filter Room
·
Vertical
cracking was identified along the northeast wall in the Filter Room directly adjacent
to the column on GL-2. This cracking is located on the north side of the column
within the first masonry block connected to the column. The cracks run the
entire height of the exterior concrete block wall and range in width from 5-10
mm where measured. The cracks have penetrated the interior face shell of the
concrete block units. It is apparent that some cracks have previously been filled
with a flexible caulking. An exterior stairway with access to the second floor
is cantilevered off of the east exterior wall using steel angle bracing as well
as through bolts to tie the stair to the existing wall.
Fire Escape hanging off of damaged wall. |
·
At
the intermediate support location, a masonry block has been displaced at the
through bolt connecting the stringer to the wall. An impression of
approximately 10 mm is present around the bolt. From the exterior it is visible
that the cracking around the through bolt has penetrated through the entire
masonry block wall thickness and through the exterior face brick. Additional
cracking is present along the exterior wall along the column line on GL-2. The
crack has previously been repaired and is now beginning to separate further. It
does not appear to fully penetrate the wall at this time.
Women's Change Room
·
During
the site visit it was brought to the attention of the AE representative that
cracking was present along the north exterior block wall at the west end of the
wall which separates the change rooms from the pool deck. The crack runs the
entire 3.05 m (10ft) height of the concrete block wall and is located
approximately 400 mm away from the northwest corner of the wall. The crack is
approximately 2-3 mm in width and has penetrated the entire wall section (both
interior and exterior face shells). The crack was traced to the women's
washroom in the west stall. The bottom of the interior crack begins at the
block out for the toilet plumbing.
·
An
additional crack was found along the southwest exterior wall along the column
line on GL-1 at the south west corner of the women's change room
Conclusions
·
From
our visual inspection as well as a desktop review of the drawings provided, it
appears that the separations between exterior face bricks located on column
lines along GL-1 & 2 are movement joints which have opened up and broke the
caulking sealant.
·
As
described above, the exterior concrete masonry wall within the northeast filter
room is lightweight concrete block unreinforced with no grouted cores. From
review it appears that the existing masonry block wall has insufficient
capacity to carry wind loads acting on the building exterior wall in combination
with axial loads from the second floor. Due to the predominant wind direction
coming from the west, the east exterior filter room wall would be subject to
wind forces "pulling" on the wall. This would cause tension in the
masonry block on the interior surface near the GL-2 column, leading to
cracking. This is consistent with the area of cracking witnessed during the
inspection.
·
In
addition to the lack of capacity to carry wind load, the cracking could be
caused by a number of other factors including differential thermal movements
between the dissimilar materials (steel vs. masonry). The columns in question
are also located within the braced bays (building bays with steel bracing rods)
with little room for expansion around the concrete masonry block.
·
The
cracking in the northwest corner of the Women's Change Room exterior blockwall
(east of GL-3) also appears to be caused by the forces described above. The
cracks observed are significant as they have completely penetrated the concrete
face shell of the masonry block. In unreinforced masonry, this is the portion
of the wall that resists both vertical and horizontal forces. If left as is,
the cracking would eventually penetrate the entire block wall thickness and
could lead to a failure of the wall.
Recommendations
·
Based
on our visual inspection and desktop review of the existing masonry wall
construction, it is recommended that the pool be kept closed until repairs can
be completed.
·
The
walls should be rehabilitated so it is stiffer.
·
The
insulation filling the hollow blocks needs to be removed.
·
The
walls are to be stiffened with reinforced grout poured into the walls.
·
The
Fire Escape stair should be taken off and replaced using posts and a different
style of wall attachments.
·
Based
on our discussions, the repairs could be done within one month of the Town
selecting a contractor. Time on site to conduct the repairs is estimated to be
1-2 weeks but is dependent on the contractor's schedule.
We have a meeting with the engineers to further discuss the report Tuesday.
We have a meeting with the engineers to further discuss the report Tuesday.
PS Notes:
·
Masonry
contractors felt that the wall may be replaced rather than rehabilitated.
·
The
insulation has to be tested for asbestos. If the results show asbestos then
another firm will have to be hired to remove the asbestos prior to work on the
wall starting.
·
The
work might be able to begin within a month and once started take only a week.
·
No
costs have been quoted at this time but it looks like it may be less than
originally anticipated.
But
Pipes exposed for inspection. |
·
We
are still determining the extent of the damage to the filter pipes and the cost
of repairing them. This may require ripping up the concrete deck, replacing the
pipes, and repouring concrete.
·
The
filter still has issues and a new pump and valves are needed.
·
I
have asked for a summary sheet of all the maintenance challenges the pool is
facing including estimated costs.
·
We
need as much information as possible so as to avoid “bankruptcy by a thousand
small repairs” (death by a thousand cuts)
Questions:
What is a reasonable cost to repair the pool? $25,000? $50,000? $100,000?
What is the minimum length of time the pool should be open?
Are ready to start a big push to fundraise for the development of Phase 2: The West Central Community Centre?
Are ready to start a big push to fundraise for the development of Phase 2: The West Central Community Centre?
To ensure our children have access to a pool: should we consider temporarily busing our children to Eatonia for swimming rather than pouring money into an aging facility?
Let me know what you think.
Let me know what you think.
No comments:
Post a Comment